Continuing with the ECA(SA)’s 2017 Presidential Excellence Awards’ winning entries, the focus is on two of Edison Power’s award-winning entries in the categories Special Innovative Projects (sponsored by Major Tech) and the Safety Award (sponsored by Nestlife). Their third award went to Gugulethuu Maseko (Edison Power Gauteng) who was named Female Apprentice of the Year (sponsored by Brother). Their project, Time Square Casino, shows why Edison stood out, Both winning apprentices will be featured later this year.

 Company’s mission and vision

The Edison Corporation is a leading new generation conglomerates engaged in various sectors within the power, energy, property development and allied businesses. The corporation rose from a modest plugs and wires business to a multi-billion-rand enterprise that leads the fields in electricity and power reticulation, power station/ sub-station / transmission infrastructure development and maintenance, state-of-the-art smart metering systems, solar energy systems and cutting-edge property development of shopping malls, casinos, commercial and residential projects. The corporation has established itself over 30 years and boasts an excellent track record for innovation, execution and total customer satisfaction.

The company’s mission is to create a productive and efficient work environment, such that it identifies with the transformation of our country in all respects, which encompasses empowerment, upliftment and job creation by implementing the best practices and working with clients of choice.

 Special Innovative Project

Sponsor: Major Tech

Awarded to: Edison Power Gauteng

Contract: Time Square Casino

Client: Sun International

Main contractor: WBHO Construction

Location: Menlyn Maine, Pretoria

Project duration: 18 months (August 2015 to March 2017)

Total value of contract: R94-million

Brief description of sub-contract works and/or services: Complete electrical installation of the new Time Square Casino at Menlyn Maine – the flagship property of Sun international and the second largest casino in South Africa. The general planning arrangement for the casino consists of a three-level super basement designed to accommodate 4 000 vehicles; a lower ground service level; the ground- and first-floor casino levels consisting of 2 000 slot machines, 60 gaming tables, and restaurants; and the second-floor roof terrace and restaurants – with a total square meterage of 193 404 m2.

The MV installation consists of an 11-panel Schneider MV RMU switchgear in the incomer substation with a 10 MVA council supply, backed by three 11 kV CAT generators. This supplies the HVAC, casino, BOH and basements, hotel and arena substations, each substation consisting of a four-panel Schneider RMU except for the casino substation, which consists of a five-panel Schneider RMU.

Eleven Schneider dry-type transformers ranging from 2 000 kVA to 3 500 kVA were installed.

There are five 120 kVA UPS units that provide uninterrupted power to the critical equipment such as emergency lighting; slot machines; fire, security, metering system, lighting control system and BMS.

All the light fittings are energy efficient LEDs: vapour-proof fittings, recessed lay-in fittings, bulkhead fittings, downlights and linear LEDs.

Materials used include: 339 distribution boards; 59 536 m cable; 798 333 m wire and earth wire; 18 821 m cable ladders/trays; 14 220 m wire trunking; 19 698 power outlets; 8 169 light fittings; 7 500 m LED ribbon; 199 m busbar; 164 552 m conduit and 339 Certificates of Compliance.

The project was completed on time and in line with the budget provision. The project was completed under extreme time pressure and co-operation between all contractors, sub-contactors and the installation teams was critical. The casino opened on the scheduled date.

 

NATIONAL SAFETY AWARD

Sponsor: Nestlife

Awarded to: Edison Power Gauteng

Contract: Time Square Casino

Client: Sun International

Main contractor: WBHO Construction

Location: Menlyn Maine, Pretoria

Project duration: 18 months (August 2015 to March 2017)

Total value of contract: R94-million

Edison Power Gauteng was on site at the Time Square Menlyn Maine Casino from November 2015 until April 2017 as the designated Electrical Contractor responsible for all permanent electrical installations for the Casino. The company is a well-recognised electrical contractor with a reputation for exceptional safety management on projects.

The safety crew on the site consisted of one Senior Site Manager; three Site Managers; four Supervisors; eight Team Leaders; one Safety Officer; one Candidate Safety Officer; and six Safety Representatives.

Safety at the Time Square Menlyn Maine Casino project was managed well, not because of any one individual’s performance, but because every person on site was committed to driving the safety culture forward. ‘I am my brother’s keeper’ was instilled as the motto for every worker to adopt with the understanding that they all should look out for each other.

Every issue that was brought to our attention by WBHO, the main contractor, was addressed immediately to avoid incidents or injuries occurring under our watch.

Onsite training

The Safety Officer was assisted in drafting his portfolio for submission to the South African Council for the Project and Construction Management Professions (SACPCMP). He was taken from the level of Safety Representative and assisted to the level where he is now qualified and registered, which is a requirement in the Construction Regulations section 8.6.

The Candidate Safety Officer was also assisted in drafting his portfolio for submission to the SACPCMP. He was also taken from the level of Safety Representative and assisted to the level where he is now registered through SACPCMP.

All Site Managers and Supervisors were trained on Legal Liability for the project and workers received training by Datamatrix for Working at Height, Scaffold Erector and Scaffold Inspector.

Audit results

Edison Power Gauteng achieved an above average audit result every month – between 90 and 100%.

At any time, there were eight first-aiders on the project who were equipped with four first aid boxes. For the duration of the contract, Edison Power Gauteng only conceded four medical conditions and eight first aid cases, all of which were minor.

Incidents

In the construction industry, inadequate safety controls affect productivity and consequently reduce profit. All the workers on site – from site managers and supervisors to team leaders and general workers – proved that a commitment to safety helps the production department to achieve the highest possible safety compliance results.

Limiting incidents contributed significantly to a profitable project with 549 491.45 hours on site. This is achievable if everyone on site works together and uses safety as a tool to deliver great workmanship, quality products, safe compliance, the meeting of client deadlines and, ultimately, to keep all workers safe from hazards and risks.